This report depicts the role and benefits of online event booking system developed for UOW. Event booking system is referred to as a web based tool that is used to manage different types of events organized by UOW. However, in order to implement such online system software professional project management skills and knowledge are needed to be acquired. In addition to this, for preparing such online system systematic phases are also required to be followed by the project team members. It is expected that, with the successful implementation of online even booking system both the staffs and students will be benefited accordingly.
In order to prepare this report a project charter is created including project title, date of commence and completion, project budget, success criteria and also the roles and responsibility of the allotted project team members. Not only project charter development but also the charter should have to be approved by all project stakeholders. After that in order to reduce the work load from the project team members the total task is segmented. The estimated project cost, resource, progress details are also illustrated in this report.
Information about the project manager
In order to develop the online event booking system the project manager is first required to understand the success criteria of the system then based on skills and knowledge the project team members should be selected. However, the project manager is responsible to make the project team members familiar to the project objectives and goals. Above all the project manager is responsible to monitor and control the project progress according to the timeline.
Based on the project objectives it can be said that the project can be completed successfully within 8 months. However, due to frequent changes in technology the project manager should make sure that even after final implementation of the online event booking system proper updates in terms of technology should be keep on incorporated. The project will be started on 20/04/2018 and expected to be finished on 27/09/2018.
After considering the software and hardware requirements it can be said that total budget around $15,550 is needed for the successful completion of the online event booking system.
project objectives
project success criteria
Roles and responsibilities of the project manager
Roles |
Responsibilities |
Project manager |
Control and monitor the project progress |
Finance manager |
To develop the project budget |
HR manager |
To manage the staffs and students associated to the project |
System developer |
To develop the system considering all necessary components of online event booking system |
System tester |
To test the event booking system |
System analyst |
To analysis the developed online event booking system |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Resource Names |
Cost |
Project schedule of Event booking system for UOW |
115 days |
Fri 4/20/18 |
Thu 9/27/18 |
$15,320.00 |
||
Project initiation phase |
34 days |
Fri 4/20/18 |
Wed 6/6/18 |
$4,440.00 |
||
Understanding details of the online event booking system |
8 days |
Fri 4/20/18 |
Tue 5/1/18 |
Project manager |
$960.00 |
|
Requirements analysis |
9 days |
Wed 5/2/18 |
Mon 5/14/18 |
2 |
Project manager |
$1,080.00 |
Feasibility study |
7 days |
Tue 5/15/18 |
Wed 5/23/18 |
3 |
Finance management |
$448.00 |
Project team development |
8 days |
Tue 5/15/18 |
Thu 5/24/18 |
3 |
HR manager |
$512.00 |
Events to be launched are analyzed |
9 days |
Thu 5/24/18 |
Tue 6/5/18 |
4 |
System developer |
$864.00 |
Time management for the events |
9 days |
Fri 5/25/18 |
Wed 6/6/18 |
5 |
HR manager |
$576.00 |
Project planning phase |
24 days |
Wed 6/6/18 |
Mon 7/9/18 |
$2,328.00 |
||
Risk management planning |
5 days |
Wed 6/6/18 |
Tue 6/12/18 |
6 |
HR manager, Project manager |
$920.00 |
Contingency and procurements planning |
8 days |
Wed 6/13/18 |
Fri 6/22/18 |
7,9 |
HR manager |
$512.00 |
Study market |
6 days |
Mon 6/25/18 |
Mon 7/2/18 |
10 |
System developer |
$576.00 |
Developing marketing strategies |
5 days |
Tue 7/3/18 |
Mon 7/9/18 |
11 |
HR manager |
$320.00 |
Project development phase |
22 days |
Tue 7/10/18 |
Wed 8/8/18 |
$4,416.00 |
||
Online system prototype design |
6 days |
Tue 7/10/18 |
Tue 7/17/18 |
12 |
System developer |
$576.00 |
Coding and design development |
8 days |
Wed 7/18/18 |
Fri 7/27/18 |
14 |
Project manager ,System developer |
$1,728.00 |
Evaluating database server |
10 days |
Wed 7/18/18 |
Tue 7/31/18 |
14 |
System developer |
$960.00 |
Incorporating online payment gateway |
6 days |
Wed 8/1/18 |
Wed 8/8/18 |
15,16 |
system analyst ,System developer |
$1,152.00 |
Testing phase |
15 days |
Thu 8/9/18 |
Wed 8/29/18 |
$1,680.00 |
||
Unit testing of the dummy |
5 days |
Thu 8/9/18 |
Wed 8/15/18 |
17 |
system analyst ,system tester |
$880.00 |
Integrated testing of the dummy |
6 days |
Thu 8/16/18 |
Thu 8/23/18 |
19 |
system tester |
$480.00 |
Facilities served by the system testing |
4 days |
Fri 8/24/18 |
Wed 8/29/18 |
20 |
system tester |
$320.00 |
Closure phase |
21 days |
Thu 8/30/18 |
Thu 9/27/18 |
$2,456.00 |
||
Stakeholders signoff |
8 days |
Thu 8/30/18 |
Mon 9/10/18 |
21 |
HR manager |
$512.00 |
Post system maintenance plan |
6 days |
Tue 9/11/18 |
Tue 9/18/18 |
23 |
Finance management, Project manager |
$1,104.00 |
Final document submission to the CIO of UOW |
7 days |
Wed 9/19/18 |
Thu 9/27/18 |
24 |
Project manager |
$840.00 |
The project scope statement is to develop and deliver an online event booking system for the staffs and students of UOW. Again the system developer should incorporate secured online payment where the consumers can book for their desired programs or even cancel.
Based on the role and responsibilities of the project manager and project team members appropriate human resource allocation are also required to be done. For different project activity proper resources should be allotted. For this particular project the allotted HR details are as follows:
Task Name |
Resource Names |
Project initiation phase |
|
Understanding details of the online event booking system |
Project manager |
Requirements analysis |
Project manager |
Feasibility study |
Finance management |
Project team development |
HR manager |
Events to be launched are analyzed |
System developer |
Time management for the events |
HR manager |
Project planning phase |
|
Risk management planning |
HR manager, Project manager |
Contingency and procurements planning |
HR manager |
Study market |
System developer |
Developing marketing strategies |
HR manager |
Project development phase |
|
Online system prototype design |
System developer |
Coding and design development |
Project manager ,System developer |
Evaluating database server |
System developer |
Incorporating online payment gateway |
system analyst ,System developer |
Testing phase |
|
Unit testing of the dummy |
system analyst ,system tester |
Integrated testing of the dummy |
system tester |
Facilities served by the system testing |
system tester |
Closure phase |
|
Stakeholders signoff |
HR manager |
Post system maintenance plan |
Finance management, Project manager |
Final document submission to the CIO of UOW |
Project manager |
In this process the project manager is required to identify the necessary requirements through which the online event management system can deliver accurate quality to the consumers. Three different components considered for developing the quality management plan is mentioned below:
Inputs: The input for successful quality management plan include project management plan, organizational process asset measurements, requirements documentation, stakeholders register, enterprise environmental factors
Tools and techniques: The tools and techniques considered for successful quality management plan include proper cost benefits analysis, consideration of quality tools, statistical sampling and quality planning tools etc.
Outputs: If these inputs and proper tools and techniques are adopted for the online event booking system then it will be able to deliver secured, on-time, affordable and quality booking opportunity to the consumers.
Risk |
Impact |
Probability |
Mitigation strategy |
Improper cost management |
High |
High |
In order to mitigate this issue, at the project initiation phase proper feasibility study is required to be done to make sure that whether the project will be successful or not. |
Lack of security approaches |
High |
Extreme |
Proper technology security in term for encryption and application firewall are to be incorporated |
Lack of business strategies |
Medium |
Low |
Professional business analysts are to be hired at the project planning phase to reduce the business oriented issues |
Incorrect resource management |
High |
Medium |
Based on the project activities the resources are to be allotted by the project manager. Again, the sponsor should allot additional cost for fulfilling further requirements |
Communication plan
Purpose for communication |
Format |
Frequency |
Whom to communicate |
Escalation |
Weekly update for status |
E-mail and video conference |
Weekly |
Project manager and project team members |
CIO |
Budget usability |
Email, conference and call |
Weekly |
Project manager and finance manager |
CIO |
Review for risk and update |
Email, conference and call |
Monthly |
CIO |
|
Risk management plan |
Email, conference and call |
Monthly |
PM and system develop |
CIO |
System review result and discussion |
Email, conference and call |
Weekly |
PM and system developer |
PM |
Completion of project initiation phase: This is the first phase of online event booking system for UOW which is accessible by the project staffs and students. According to the details of online event booking system requirements in the project initiation phase the developers are required to understand the system requirements then requirements should be analyzed accordingly. After analyzing the requirements the events to be launched and analyzed and time management plan must be developed based on the requirements.
Completion of project planning phase: In the project planning phase after analyzing the market proper risk management, quality management, change management, procurement and contingency management plan is needed to be developed by the project manager. Besides this accurate market development strategies are developed in this phase.
Completion of project development phase: After developing proper project planning the online event system should be developed considering proper programming and coding. Online payment gateway option is also available to allow the users easily access the payment system. Connections with the database are also developed in this phase. It has been found that, secured online payment will allow the consumers to book for their desired events regardless of their location and time.
Completion of project testing phase: After developing the system the online event booking system is tested by the system tester and system analyst. If it is found that any additional changes are needed then according to the additional requirements requests for necessary changes are be done and hat request should be approved by the project manager.
Completion of project implementation phase: After final testing of the event booking system it should be approved and launched rather implemented after final approval. However, with the completion and implementation of the system the responsibilities of the stakeholders are not finished. Rather the stakeholders are associated to the post project maintenance planning also. In this phase the ongoing success of the online event booking system developed for UOW are analyzed. Whether the system needs any changes or not is also measured in this phase.
After the completion of the online event booking system it has been found that, the there is no such long term difference between the project success against the initial plan. The project has met all the success criteria according to the scope and assumption criteria.
Yes, the project has met the estimated time, cost and goal that have been assumed at the project initiation and project planning phase. However, all the security approaches in terms of firewall and encryption are not considered by the system developers. It is the responsibility of the project manager to measure the project progress to control and monitor the necessary criteria.
The experiences gathered during the development of the project, ideas regarding cost management, cash flow determination, and time management and also how to manage the quality of a project are also gathered and it is expected that these ideas can be used for further project development.
Conclusion
From the overall discussion it can be said that with the successful implementation of the online booking system the consumers and the staffs of UOW will be able to deliver and create different promotional activities and event details in their official website. The consumers of the system can view the details list of events, launch new events, available dates, adjust the price and also can make and even cancel booking as per their desire. In order to develop the online booking system, proper project planning, execution and closure plan detailing resource management, stakeholder management, cost management, quality and risk management plan are also developed in this report. Besides these in order to prepare the online booking system the other criteria in terms of project management skills and product development capabilities are also considered by the project developing team members.
References
Bresnen, M., 2016. Institutional development, divergence and change in the discipline of project management. International journal of project management, 34(2), pp.328-338.
Costantino, F., Di Gravio, G. and Nonino, F., 2015. Project selection in project portfolio management: An artificial neural network model based on critical success factors. International Journal of Project Management, 33(8), pp.1744-1754.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge Sharing in Project Management–a Relationship Model.
Martens, M.L. and Carvalho, M.M., 2017. Key factors of sustainability in project management context: A survey exploring the project managers’ perspective. International Journal of Project Management, 35(6), pp.1084-1102.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Salameh, H., 2014. A framework to establish a project management office. European Journal of Business and Management, 6(9), 19-26.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Succar, B., Sher, W., & Williams, A., 2013. An integrated approach to BIM competency assessment, acquisition and application. Automation in Construction, 35, 174-189.
Takey, S.M. and de Carvalho, M.M., 2015. Competency mapping in project management: An action research study in an engineering company. International Journal of Project Management, 33(4), pp.784-796.
Thamhain, H., 2013. Managing risks in complex projects. Project Management Journal, 44(2), 20-35.
Varajao, J., Dominguez, C., Ribeiro, P., & Paiva, A., 2014. Critical success aspects in project management: similarities and differences between the construction and software industry. Tehni?ki vjesnik, 21(3), 583-589.
vom Brocke, J., & Lippe, S. (2015). Managing collaborative research projects: A synthesis of project management literature and directives for future research. International Journal of Project Management, 33(5), 1022-1039.
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.