Instructions 

Students will revise as required their previous submission based on instructor feedback, and then add the following three sections. The resulting submission will include all seven sections to date.

  • Develop the Quality Management Plan.  This anticipates who in the organization will take responsibilities for aspects of the project and their role.  This will be used when the project implementation begins.
  • This should be a spreadsheet or grid as found on pages 117 and 118 in the textbook. 
  • Assign Resources to the Project software document.  
  • Create a Communication Plan. Submit as a 1-2 page MS Word document or MS Excel document, using a grid plus text) See the example in Figure 4:10, page 122 of A Guide to the Project Management Body of Knowledge: PMBOK® Guide.

PMBOK is a registered mark of the Project Management Institute, Inc.

Reference PMBOK

Reference attached Docs

2

>Intro

erm Project Part

hannon Brain

Project Planning Essentials

6-

eb-2

Individual

T 3
S
Yorkville University
BUSI 3

6 23
1 F 0

Budget

anning

Budget

00,000

5,000.00

3,000.00

,000.00

0.00

50.00

0.00

0.00

$1,000.00

0.00

,500.00

$5,000.00

Customer changes

1,100.00

00.00

$1,250.00

$3,000.00

indow/Doors

$50,000.00 50,000.00

10,000.00 $0.00

,500.00

Reports

$1,000.00

-$1,500.00 Additional reports requested

$7,000.00

$3,000.00 3,200.00 -$200.00

$5,000.00

,000.00

$2,000.00

-$2,000.00

$20,000.00

,009.00

Added Features

,000.00

0.00

Family House Construction Plan
Project Owner:

Joseph

M
$

5
Requirement Anaylsis Planned Actual (+/-) Comments
Engineering project reports $1

4 12 $

22
Product quality checks report $3,000.00 3,

20 -$200.00 Additional reports requested
Design documents $5,000.00 4,

8 $

15
Proposals $1,000.00 1,

25 -$250.00 Updated quote
Drawings 1,

10 -$100.00 Customer changes
Survey/Prepare Site $

7 6,250.00 $1,250.00
Design structural components 6,000.00 -$1,000.00
House assessment report $2,000.00 $

9
Install Foundation $75,000.00 82,000.00

$7,000.00 Rework cement
Frame $25,000.00 23,750.00
Roof install $

50,000.00 47,000.00
W $0.00
   Power connection $

10,000.00
Water connection $12,000.00 13 -$1,500.00 Change in scope
Progress 2,500.00
Drywall install 9,000.00 -$2,000.00 Additional labour
Trim
Paint 4,400.00 $600.00
Floor install $20,000.00 18
Kitchen Install $40,000.00 42,000.00 Added Features
Bathroom install 26 -$6,009.00
Grade Yard $10,000.00 26,000.00 -$

16 Driveway added
Build Inspection $2,500.00 2,200.00 $

30
Total $500,000.00 $506,309.00 -$6,309.00 Result :
Over Budget

Gantt Timeline

Family House Construction Project

date in cell F3 or allow the sample formula to find the smallest date value from the Gantt Data table.

label is in cell D3.

Joseph Manning Project Start Date:

0

1 2 3 4 5 6 7 8 9 10

12 13

15 16

18

20

22 23

25 26

30

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

s table.

Progress Start

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Requirement Anaylsis Milestone

8

Engineering project reports On Track T Smith

2

Product quality checks report

3

Design documents On Track A Solce 100% 1/1/20 30
Proposals Low Risk T Smith

10

Drawings Milestone A Solce 100%

14 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Survey/Prepare Site Milestone

100%

7

Design structural components Milestone J Baker 100%

10

House assessment report Milestone

100%

6

Install Foundation Milestone J Baker 75%

14

Frame On Track

0%

14

Roof install On Track L Coal 0%

7

Milestone

0% 3/13/20 4

   Power connection On Track

0%

7

Water connection On Track L Coal 0% 3/14/20 7

Low Risk T Smith 0% 3/19/20 11

Drywall install On Track J Baker 0%

14

Trim On Track J Baker 0%

7

Paint On Track J Baker 0%

14

Floor install Goal J Baker 0%

21

Kitchen Install Goal J Baker 0%

5

Bathroom install Low Risk J Baker 0% 5/12/20 4
Grade Yard Milestone J Baker 0% 4/20/20 2
Build Inspection Milestone J Baker 0%

1

Milestone J Baker 0%

1

Create a Gantt Chart in this worksheet.
Enter title of this project in cell B1.
Legend title is in cell I1.
Information about how to use this worksheet, including instructions for screen readers and the author of this workbook is in the About worksheet.
Continue navigating down column A to hear further instructions.
Family House Construction Project Legend:
Enter Company Name in cell B2.
A legend is in cells I2 through AC2.
On Track Low Risk Med Risk High Risk Unassigned
Enter the name of the Project Lead in cell B3. Enter the Project

Start Project Start Date: 1/1/20
A Scrolling Increment is in cell F4.
Months for the dates in row 5 are displayed starting in cells I4 through cell BL4.
Do not modify these cells. They are auto updated based on the project start date in cell F3.
Scrolling Increment: January February
Cells I5 through BL5 contain the day number of the month for the Month represented in the cell block above each date cell and are auto calculated.
Do not modify these cells.
Today’s date is outlined in Red (hex #AD3815) from today’s date in row 5 through the entire date column to the end of the project schedule.
11 14 17 19 21 24 27 28 29 31
A scrollbar is in cells I6 through BL6. The increment for paging through the data is defined as 2 pages at a time and can be configured in the settings for the control bar.
To jump forward or backward in the timeline, enter a value of 0 or higher in cell F4.
A value of 0 takes you to the beginning of the chart.
This row contains headers for the project schedule that follows below them.
Navigate from B7 through BL7 to hear the content. The first letter of each day of the week for the date above that heading, starts in cell I7 and continues through cell BL7.
All project timeline charting is auto generated based on the category, start date and number of days entered in the

Milestone Milestone Description Category Assigned To No. Days Column1
Do not delete this row. This row is hidden to preserve a formula that is used to highlight the current day within the project schedule.
T Smith 10

0% 1/11/20
Enter Project information starting in cell B9 through cell G9.
Sample data is in cells B9 through G33.
Enter Milestone Description, select a Category from the drop-down list, assign someone to the item, enter the progress, start date and number of days for the task to start charting.
The next instruction is in cell A34.
59% 2/14/19
Goal A Solce 75% 3/13/20
90% 3/10/20
1/22/20
J Baker 2/5/20
Design structura;Componentns 1/29/20
Jbaker 3/19/20
2/14/20
L Coal 2/28/20
3/6/20
Window/Doors Graybar
C Docker 3/14/20
Progress Reports
3/23/20
4/6/20
4/7/20
4/20/20
5/12/20
5/15/20
Walk thru/Final Acceptance 5/30/20

2

>Sheet

3

1

Months

20

1

2

3

Complete

4

Not Complete

7

Complete

6

#5 Complete 30

7

Complete 30

8

Complete 30

Complete 30

Not Complete 30

Not Complete

Not Complete 35

Not Complete 35

Not Complete 35

Not Complete

Not Complete 46

Complete

Complete

Complete

20

Not Complete

Not Complete 50

Preparation of site

Not Complete

Relocating services

Not Complete

Piling (stakes)

Not Complete

Constructing foundation

Not Complete

Erecting pylons

Not Complete

Filling the concretes

Not Complete

Complete

Detailed design

Complete

30 Architectural design

Complete

Drawing the plan

Not Complete

Preparation of site

Not Complete

Relocating services

Not Complete

Piling (stakes)

Not Complete

Project Name Family House Project Project # 1 4
Project Manager’s Name Joseph Dunhill Sponsor 0
Project Timeframe 6 Updated 2.2.

20
Project Stages WBS Code Task/ Deliverables Dependencies Status
Author: Options are:
Open
Closed
Effort Hours
Needs/ Requirements Assessment Site Investigation ID #1 Complete 42
Detailed Planning #2 Not Complete 43
Identifying Labor Requirements #3 6

7
Identifying Machine and Technology Requirements #4 8
5 Assessing Financial Needs/ Requirements #5 30
Determining the Time Needed
Assessing the Building materials Requirements #6
Design and Analysis Detailed Design #7
9 Architectural Design #8
10 Drawing the Plan #9
Development Phase 11 Preparation of site #10 35
12 Relocating services #11
13 Piling (stakes) #12
14 Constructing foundation #13
15 Erecting pylons #14 46
16 Filling the concretes #15
17 Assessing the building materials Requirements #16 45
18 Detailed design #17 47
19 Architectural design #18 49
Drawing the plan #19 50
21 Design approval #20
Completion and Implementation 22 #21 52
23 #22 54
24 #23 56
25 #24 58
26 #25 59
Testing 27 #26 61
28 Assessing the building materials requirements #27 63
29 #28 65
#29 67
Repair and Maintenance 31 #30 68
32 #31 70
33 #32 72
34 #33 74

Running head: PROJECT SCOPE STATEMENT 1

PROJECT SCOPE STATEMENT 6

Individual Term Project Part 2

Shannon Brain

Yorkville University

BUSI 3623 Project Planning Essentials

February 1, 2020

Project Scope Statement

1. The project name: Family House Construction Project

2. The project charter

This project focuses on designing, developing, and completing a detached house for a family in Toronto, Ontario. The house shall be constructed in full compliance with the City Planning Regulations, as well as the recommended construction safety standards. As part of the construction process, the road to the building will be planned and will be wholly surfaced. Moreover, potable water will be piped from the mains municipality water supply. The piped water will be connected by designing a canal to the front of the plot or site. Once complete, electric power connection will be linked to the house from the mains supply.

3. The project owner, sponsors, and stakeholders

The project is owned by Dominic Schwab, a businessman based in Toronto. Manning is the client whose house should be completed. The key stakeholders of the project include: employees, who include architect, engineer, trade contractor, as well as material suppliers. While the project is fully owned by the client, it is partly sponsored by the Ministry of Municipal Affairs and Housing, partly sponsors the development of decent housing for the low- and middle class societies.

4. Problem Statement

The housing crisis among the low- and middle-class populations is increasingly becoming a major concern for both Federal and Provincial Governments. In the last five years, The Canada and US has witnessed an upsurge in shanty houses. The mushrooming of slums across different towns and cities is indicative of the increase in the number of low- and middle-income people who cannot afford decent housing (Fields & Hodkinson, 2018). Moreover, government regulators and authorities are concerned with the need to prevent rental homes from being converted to market-rate housing or demolished to keep them affordable and available to low-income households. Policymakers also seek to develop interventions that can increase access to affordable housing facilities for low-income families.

5. The project goals and objectives

Goals

a) To complete a five-bedroom house for a family within 6 months.

b) To develop a high-quality house.

Objectives

a. To assess the site and determine the housing needs for the family

b. To examine the budget for each item and resources

c. To design the foundation and complete the building

d. To conduct quality and safety assessment of the completed building

e. To connect water and electricity to the completed house

6. The project requirements

Requirements are the resources and activities that will be needed to complete the project. Determining the project requirements is a critical step in determining what the project team can use to successfully implement the construction project (Sokowski, 2015).  The key requirements for the project will include:

a. Labor requirements

b. Financial requirements

c. Construction equipment

d. Construction machines

e. Building materials

7. The project deliverables

Project deliverables refer to the outputs that should be completed upon closure of the project. It is the task of the project manager to determine, track, and manage project deliverables for each task that has been assigned (Moustafaev, 2014). For this particular construction project, the list of project deliverables includes:

a. Engineering project reports

b. Product quality checks report

c. Design documents

d. Proposals

e. Drawing

f. House assessment report

g. The completed family house

h. Power connection

i. Water connection

j. Progress Reports

8. The project non-goals (what is out of scope)

The purpose of the project will be to complete a 5-bedroom family house. As such, there are various items that will be out of the scope for the project. Examples of items that will be out of scope include:

a. Fencing the construction site

b. Furnishing the house

c. Landscaping the compound

9. Milestones

Activity

From

To

1

Requirements Analysis

February 2, 2020

February 10, 2020

2

Surveying and preparing the site

February 11, 2020

February 25, 2020

3

Designing the structural components

February 26, 2020

February 29, 2020

4

Constructing foundation

March 1, 2020

March 10, 2020

5

Electrical system installation

March 11, 2020

March 22, 2020

6

Roadway surfacing

March 23, 2020

March 31, 2020

7

Fitting the windows doors

April 1, 2020

April 10, 2020

8

Obtain inspection approvals

April 20, 2020

April 24, 2020

10. Cost estimates

Item

Cost (CAD)

1

Labor Costs

$150,000

2

Construction equipment and machines

50,000

3

Purchasing building materials

250,000

4

Purchasing windows

5,000

5

Purchasing doors

5,000

6

Installing electric power

20,000

7

Water pipe connections

20,000

TOTAL

$500,000

References

Fields, D. J., & Hodkinson, S. N. (2018). Housing policy in crisis: An international perspective.

Journal of Housing Policy Debate, 28 (1), 1-5.

“Ministry of Municipal Affairs and Housing.” www.ontario.ca/page/ministry-municipal-affairs-housing.

Moustafaev, J. (2014). Project scope management: A practical guide to requirements for

engineering, product, construction, IT and enterprise projects. New York: Auerbach

Publications.

Sokowski, D. (2015). Mastering Project Management Integration and Scope: A Framework for

Strategizing and Defining Project Objectives and Deliverables. New York: FT Press.

Quality Management Plan

Project Management Improvement Project

Example

Prepared By: Name

1

Project Manager

Position:
Project manager

Date:
January

2

7, 2006

Version No:
v

1.0

Document Change Control

The following is the document control for revisions to this document.

Version Number

Date of Issue

Author(s)

Brief Description of Change

0.9

11/15/05

Name1 – Project Manager

Phase 1 – Preliminary draft for Phase 1

1.0

1/27/06

Name1 – Project Manager

Phase 1 & 2 – conform to new framework template, update for Phase 2 deliverables

Definition

The following are definitions of terms, abbreviations and acronyms used in this document.

Term

Definition

PMA

Project Management Advisor

Web tool

Table Of Contents

1

1. Quality Management Approach

2

2. Quality Management Objectives

3

3. Project Quality Control

6

4. Project Quality Assurance

7

5. Quality Team Roles & Responsibilities

9

6. Quality Tools

10

7. Quality Control and Assurance Problem Reporting Plan

11

8. Appendix

11

Gap Resolution Targets

1. Quality Management Approach

The purpose for managing quality is to validate that the project deliverables are completed with an acceptable level of quality. Quality management assures the quality of the project deliverables and the quality of the processes used to manage and create the deliverables.

The quality management plan identifies these key components:

Objects of quality review

Quality Measure

Quality Evaluation Methods

Project Deliverables

Deliverable Quality Standards

Completeness and Correctness Criteria

Quality Control Activities

Project Processes

Process Quality Standards

Stakeholder Expectations

Quality Assurance Activities

The following is a brief explanation of each of the components of the quality management plan.

Project Deliverables and Processes

The key project deliverables and processes subject to quality review.

Deliverable

Quality Standards

and

Completeness and Correctness Criteria

The quality standards that are the “measures” used to determine a successful outcome for a deliverable.

The completeness and correctness criteria describe when each deliverable is complete and correct as defined by the customer. Deliverables are evaluated against these criteria before they are formally approved.

Process

Quality Standards

and

Stakeholder Expectations

The quality standards that are the “measures” used to determine if project work processes are being followed.

Stakeholder expectations describe when a project process is effective as defined by the project stakeholders. An example is the expectation to be regularly informed monthly of project status.

Quality Control Activities

The quality control activities that monitor and verify that the project deliverables meet defined quality standards.

Quality Assurance Activities

The quality assurance activities that monitor and verify that the processes used to manage and create the deliverables are followed and are effective.

2. Quality Management Objectives

The following are the quality objectives of the project that reflect the overall intentions to be applied with regard to quality throughout the project.

· Deliverables support improved project management proficiency at DoIT

· Deliverables meet the requirements of DoIT leaders and project managers

· Deliverables align with industry best practices for project management and Web delivery

· Deliverables are easy to use

· Project practices conform to recommended project management standards

3. Project Quality Control

The focus of quality control is on the deliverables of the project. Quality control monitors project deliverables to verify that the deliverables are of acceptable quality and are complete and correct.

The following table identifies:

· The major deliverables of the project that will be tested for satisfactory quality level.

· The quality standards and the correctness and completeness criteria established for the project deliverable. Included are any organizational standards that need to be followed.

· The quality control activities that will be executed to monitor the quality of the deliverables.

· How often or when the quality control activity will be performed.

Review Team review

Framework

Framework

Framework

Project Management Advisor (PMA)

Project Management Advisor (PMA)

Once prior to each phase/interim version release

Project Management Advisor (PMA)

Project Management Advisor (PMA)

Project Management Workshop

Core Team review

Project Deliverable

Deliverable Quality Standards/

Completeness and Correctness Criteria

Quality Control Activity

Frequency/Interval

Framework

QC1. Conforms to expert commentary regarding clarity and conciseness (95%)

Information mapping

Technical editor review

Core Team review

Weekly

by topic

Weekly

by topic .

Weekly by topic

Monthly

QC2. Aligned with industry best practices (90%)

Project Management Institute alignment per Project Management Book of Knowledge, 3rd edition

Core Team review
Review Team review

Once during overall framework design

Weekly by topic

Monthly

QC3. Aligned with UW best practices (90%)

UW Office of Quality Improvement alignment per Symposium 2006 training and documentation

Review Team review

Once during overall framework design

Monthly

QC4. Apply prioritized changes per Review Team review (95%)

Document, prioritize, publish change requests

Apply change requests per Project Management – Review Team Commentary by Action (1/6/06) and update change control documentation

Monthly
Weekly

Project Management Advisor (PMA)

QC5. Meets ease of use criteria (90%)

Establish & document evaluation criteria

Preliminary prototype feedback per criteria

Review Team review per criteria

Usability test per criteria

Once during initial prototype design

Weekly during prototype design

Monthly

.

Once prior to each phase/interim version release

conclusions

QC6. Meets UW Web accessibility standards per
http://www.wisc.edu/policy/wwwap.php

See:
http://helpdesk.doit.wisc.edu/page.php?id=1157

(Phase 1 – 90%) (Phase 2 – 100%)

DoIT accessibility standards committee review

Once prior to each phase/interim version release

QC7. Supports cross-browser access per Help Desk documentation
http://helpdesk.doit.wisc.edu/page.php?id=3207

(Phase 1 – 90%) (Phase 2 – 100%)

Cross-browser test by Help Desk

QC8. Accurate incorporation of framework into PMA (100%)

Apply version control to all PMA changes (100%)

Routine framework developer audit of PMA

Weekly during each change cycle

QC9. Completeness and correctness of Web linking (100%)

Routine framework developer audit

Final go-live test

Monthly testing .

Once prior to each phase/interim version release

Project Management Workshop

QC10. Structured per good training standards (95%)

Delivery consultation by training provider

Biweekly during workshop design

QC11. Accurate communication of framework (95%)

Biweekly during workshop development

Project Management Training Plan

QC12. Addresses all DoIT project management skill levels (95%)

Group manager survey

Group manager review

Core Team review .

Sponsor review

Once during plan design

Once prior to plan publication

Monthly during plan development

Monthly during plan development

Resolve project management gaps per Appendix A

QA13. Gaps resolved per Appendix A (100%)

Assessment and reporting of satisfactory gap resolution

Once per project phase

completion

4. Project Quality Assurance

The focus of quality assurance is on the processes used in the project. Quality assurance ensures that project processes are used effectively to produce quality project deliverables.

The following table identifies:

· The project processes subject to quality assurance.

· The quality standards and stakeholder expectations for that process.

· The quality assurance activity – such as a quality audit or reviews – that will be executed to monitor that project processes are properly followed.

· How often or when the quality assurance activity will be performed.

Frequency/Interval

Project Process

Process Quality Standards/

Stakeholder Expectations

Quality Assurance Activity

QA1. Develop/refine project charter

QA2. Develop/refine project plan

QA3. Execute and control project per project plan

QA4. Approve each project stage

QA5. Close project with post project review

100% compliance with framework

100% compliance with framework

95% compliance with framework

100% compliance with framework

100% compliance with framework

Audit charter updates by phase

Audit plan content and updates, project priorities, and task estimation

Audit the following project activities:

· Quality

· Communications

· Project progress

Audit stage checkpoints

Audit project reviews by phase

Once per project phase

Once per project phase
Weekly

Monthly

Monthly

Once per project phase/stage

Once per project phase

5. Quality Team Roles & Responsibilities

The following identifies the quality-related responsibilities of the project team and lists specific quality responsibilities.

Name1 – Project Manager

Project Team Role

Assigned Resource

Quality Control and Quality Assurance Responsibilities

Executive Sponsor .

Project Sponsor

Name3 – Executive Sponsor .

Name2 – Project Sponsor

QA4: Approve each project stage per framework checkpoints

QA1, QA2, QA3, QA5: Assess practice of project management framework activities

QC13: Assess satisfactory resolution of project management gaps

Project Manager

QA3: Assure practice of quality control measures and communications in project plan

QC1, QC2, QC5: Assure framework and PMA reviews by Core Team, Review Team, usability testers, Web accessibility testers, cross-browser testers

QC1, QC2, QC5: Communicate prioritized changes per Review Team review

QC3, QC4: Assure deliverables meet broad set of UW and DoIT project manager requirements

QC12: Assure training plan addresses all DoIT project management skill levels

QC13: Assure project management gap resolution

Lead Framework Developer

Phase 1 – Name4

Phase 2 – Name5

QC6: Confirm PMA meets Web accessibility standards

QC7: Confirm PMA provides cross-browser access

QC8, QC9: Test PMA for accurate delivery of framework and completeness of linking

Core Team Member

Name1 – Project Manager, Name4, Name6, Name5

QC4: Prioritize changes per Review Team review

QC11: Assure workshop accurately delivers framework

Technical Editor

Name7

QC1: Edit framework to assure it is clear and concise

Web Accessibility Committee

DoIT committee

QC6: Test PMA for Web accessibility

Cross-Browser Testers

DoIT Help Desk

QC7: Test PMA for cross-browser support

Training Consultant

Name8

QC10: Assure workshop structured per good training standards

6. Quality Tools

The following lists the tools to be used to support quality management implementation and the purpose or use of the tool.

Tool Name

Tool Purpose/Use

Project Management Advisor

Document the project management framework stages and activities to be applied to this project

Project Management Framework Templates

Document the project management deliverables to be produced by this project

My Webspace Phased Deliverables Directories

Directory structure used for version control of framework and PMA

My Webspace Phased Review Team Feedback Directories

Directory structure used for comments and change requirements from the Review Team and the Usability testers

Web Accessibility Testing Tool: Bobby

Used to test PMA compliance with Web accessibility standards.

DoIT Help Desk Browser Testing Standards

Used to test PMA compliance with Web browser support standards.

7. Quality Control and Assurance Problem Reporting Plan

Quality was managed rigorously but informally during Phase 1. Beginning with the initiation of Phase 2, this project will manage quality according to this quality management plan. The project manager will monitor quality and report exceptions to the executive sponsor and the project sponsor as part of monthly status reporting, or more frequently if conditions warrant.

The following logs will be used to itemize, document and track to closure items reported through quality management activities.

Quality Control Log

Exception ID Number

Review Date

Deliverable Reviewed

Findings

Resolution

Resolution Date

QC-Exc-1

QC-Exc-2

Quality Assurance Log

Exception ID Number

Review Date

Findings

Resolution

Resolution Date

Process Reviewed

QA-Exc-1

QA-Exc-2

8. Appendix

Gap Resolution Targets

DoIT conducted a study in 2005 to assess gaps in DoIT’s project management practices. Appendix A summarizes gap findings and identifies the targeted Project Management Improvement project phase for resolving each gap. See Appendix B for the gap assessment report.

Table 1 lists each gap and identifies (1) the means to progress toward resolution of the gap via the project management framework and (2) a targeted phase for resolution. Tables 2 and 3 summarize the gaps targeted for resolution in Phases 1 and 2, respectively. Table4 summarize the gaps targeted for resolution in Phases 3 and beyond. Target dates for completion of project phases are specified in the project plan.

In general, the framework alone will not resolve gaps. Rather, organizational implementation of the framework is necessary, including implementation of appropriate tools and training as well as adjustment of thinking and culture to align with the framework. This is reflected in the targeted phase for resolution, which often is later than the expected completion of the indicated framework components.

For each phase of the project management improvement project, the project manager will plan, execute, and control progress toward resolution of gaps as specified below. The project sponsor and project manager will assess and report satisfactory resolution of these gaps as part of the acceptance checkpoint at the end of each project phase.

Table 1 – Gap Resolution Plan by Category

This table itemizes all gaps identified in the 2005 study and maps the resolution plan the project management framework and a project phase for framework implementation.

1 – Conceptualize

Strategic Alignment

3+

1 – Conceptualize

Strategic Alignment

3+

1 – Conceptualize

Strategic Alignment

3+

1 – Conceptualize

Strategic Alignment

2-3

2-3

1 – Conceptualize 2 – Initiate

2

2

1 – Conceptualize

Role Management

2

Role Management

2

All

2

All

All

All

1

All

All

1

2

All

All

2

All

All

2

2

Gap Category

Gap

Project Management Framework Stage

Project Management Framework Activity

Project Management Improvement Phase

Cross-Unit Leadership

1. Inadequate assessment of interdependences between projects in terms of resource allocation and customer impact

1 – Conceptualize

Strategic Alignment

3+

2. Inadequate controls on project definition, launch, and impact on other projects

3. Inadequate controls on project priority setting

4. Inadequate controls for major project commitments, timelines, and interdependences

Unit Leadership

1. Inadequate setting of project’s rationale and strategic goals

2-3

2. Inadequate explicit communications of project’s rational and strategic goals

1 – Conceptualize 2 – Initiate

Communication Management

3. Inadequate controls identifying and verifying customer need

1 – Conceptualize 2 – Initiate

Scope Management

Requirements Management

4. Inadequate controls identifying and verifying sponsor support

Role Management

5. Inadequate working relationship with customers during project phases

All

Role Management

Communication Management

Project Management Culture

1. Inadequate control for unit leaders to determine which projects need or do not need formal project management

Project Management Culture (cont.)

2. Inadequate control for determining skill levels needed for project manager

1 – Conceptualize

2 – Initiate

3. Project Managers do not necessarily have formal project management training

All

4. Lack of processes for project initiation, go/no-go, move from project to production

Checkpoints

1-2

5. Need for project management process

6. Need for decision and process strategies

7. Inadequate pricing strategy for customers

2 – Initiate 3 – Plan

Budget Management

8. Need for a “Project Management Apprentice Program”

9. Distribution of templates designed as helpful approaches

10. Need for customers to participate in functional requirements workshops

2 – Initiate Scope Management

Requirements Management

Role Management

Table 2 – Targeted Gap Resolution for Phase 1

This table summarizes the gaps targeted for resolution at the conclusion of Phase 1.

Gap Category

Gap

Project Management Culture

5. Need for project management process

All

All

1

6. Need for decision and process strategies

All

All

1

4. Lack of processes for project initiation, go/no-go, move from project to production

All

Checkpoints

1-2

Framework Stage

Framework Activity

Improvement Phase

Table 3 – Targeted Gap Resolution for Phase 2

This table summarizes the gaps targeted for resolution at the conclusion of Phase 2.

Gap Category

Gap

Framework Stage

Framework Activity

Improvement Phase

Unit Leadership

1. Inadequate setting of project’s rationale and strategic goals

1 – Conceptualize

Strategic Alignment

2-3

2. Inadequate explicit communications of project’s rational and strategic goals

1 – Conceptualize 2 – Initiate

Communication Management

2-3

3. Inadequate controls identifying and verifying customer need

1 – Conceptualize 2 – Initiate

Scope Management
Requirements Management

2-3

4. Inadequate controls identifying and verifying sponsor support

1 – Conceptualize 2 – Initiate

Role Management

2

5. Inadequate working relationship with customers during project phases

All

Role Management
Communication Management

2

Project Management Culture

1. Inadequate control for unit leaders to determine which projects need or do not need formal project management

1 – Conceptualize

Role Management

2

2. Inadequate control for determining skill levels needed for project manager

1 – Conceptualize 2 – Initiate

Role Management

2

3. Project Managers do not necessarily have formal project management training

All

All

2

4. Lack of processes for project initiation, go/no-go, move from project to production

All

Checkpoints

1-2

7. Inadequate pricing strategy for customers

Budget Management

2

8. Need for a “Project Management Apprentice Program”

All

All

2

9. Distribution of templates designed as helpful approaches

All

All

2

10. Need for customers to participate in functional requirements workshops

2 – Initiate

Scope Management
Requirements Management
Role Management

2

2 – Initiate 3 – Plan

Project Management Culture (cont.)

Table 4 – Targeted Gap Resolution for Phase 3 and Beyond

This table summarizes the gaps targeted for resolution at the conclusion of Phase 3 and beyond.

Gap Category

Gap

Framework Stage

Framework Activity

Improvement Phase

Cross-Unit Leadership

1. Inadequate assessment of interdependences between projects in terms of resource allocation and customer impact

1 – Conceptualize

Strategic Alignment

3+

2. Inadequate controls on project definition, launch, and impact on other projects

1 – Conceptualize

Strategic Alignment

3+

3. Inadequate controls on project priority setting

1 – Conceptualize

Strategic Alignment

3+

4. Inadequate controls for major project commitments, timelines, and interdependences

1 – Conceptualize

Strategic Alignment

3+

Unit Leadership

1. Inadequate setting of project’s rationale and strategic goals

1 – Conceptualize

Strategic Alignment

2-3

2. Inadequate explicit communications of project’s rational and strategic goals

1 – Conceptualize 2 – Initiate

Communication Management

2-3

3. Inadequate controls identifying and verifying customer need

1 – Conceptualize 2 – Initiate

Scope Management
Requirements Management

2-3

Disclaimer

This example is based on a real project. However, this version is changed to present full examples of Quality Management Plan components as described in the DoIT Project Management Framework. This example is not a true representation of the Quality Management Plan for the Project Management Improvement project.

Example – Project Management Improvement Project – Quality Management Plan, v1.0.1
Page ii

122 Part 1 – Guide

Figure 4-15. Close Project or Phase: Data Flow Diagram

• Project
charter

5.5
Validate
Scope

12.1

Plan

Procurement
Management

4.1
Develop

Project Charter

Project
Management

Plan

Project
Documents

Project
Documents

4.7
Close

Project or
Phase

Enterprise/
Organization

Enterprise/
Organization

Customer

• Accepted deliverables

• Project Charter

• Procurement documentation

12.2
Conduct

Procurements

• Organizational process assets

• Final product, service, or
result transition

Project documents updates
• Lessons learned register

• Final report
• Organizational process
assets updates

Project management plan
• All components

Project documents
• Assumption log
• Basis of estimates
• Change log
• Issue log
• Lessons learned register
• Milestone list
• Project communications
• Quality control measurements
• Quality reports
• Requirements documentation
• Risk register
• Risk report

Business
Documents

• Agreements • Business case
• Benefits management plan

Co
py
ri
gh
t
©
2
01
7.
P
ro

je
ct
M
an
ag
em
en
t
In
st
it
ut
e.
A
ll
r
ig
ht
s
re
se
rv
ed
.
Ma
y
no
t
be
r
ep
ro
du
ce
d
in
a
ny
f
or
m
wi
th
ou
t
pe
rm
is
si
on
f
ro
m
th
e
pu
bl
is
he
r,
e
xc
ep
t
fa
ir
u
se
s
pe
rm
it
te
d
un
de
r
U.
S.

or
a
pp
li
ca
bl
e
co
py
ri
gh
t
la
w.

EBSCO Publishing : eBook Collection (EBSCOhost) – printed on 3/13/2020 4:15 PM via YORKVILLE UNIV
AN: 1595320 ; Project Management Institute.; A Guide to the Project Management Body of Knowledge (PMBOK® Guide)–Sixth Edition
Account: s7439054

122 Part 1 – Guide

Figure 4-15. Close Project or Phase: Data Flow Diagram

• Project
charter

5.5
Validate
Scope

12.1

Plan

Procurement
Management

4.1
Develop

Project Charter

Project
Management

Plan

Project
Documents

Project
Documents

4.7
Close

Project or
Phase

Enterprise/
Organization

Enterprise/
Organization

Customer

• Accepted deliverables

• Project Charter

• Procurement documentation

12.2
Conduct

Procurements

• Organizational process assets

• Final product, service, or
result transition

Project documents updates
• Lessons learned register

• Final report
• Organizational process
assets updates

Project management plan
• All components

Project documents
• Assumption log
• Basis of estimates
• Change log
• Issue log
• Lessons learned register
• Milestone list
• Project communications
• Quality control measurements
• Quality reports
• Requirements documentation
• Risk register
• Risk report

Business
Documents

• Agreements • Business case
• Benefits management plan

Co
py
ri
gh
t
©
2
01
7.
P
ro

je
ct
M
an
ag
em
en
t
In
st
it
ut
e.
A
ll
r
ig
ht
s
re
se
rv
ed
.
Ma
y
no
t
be
r
ep
ro
du
ce
d
in
a
ny
f
or
m
wi
th
ou
t
pe
rm
is
si
on
f
ro
m
th
e
pu
bl
is
he
r,
e
xc
ep
t
fa
ir
u
se
s
pe
rm
it
te
d
un
de
r
U.
S.

or
a
pp
li
ca
bl
e
co
py
ri
gh
t
la
w.

EBSCO Publishing : eBook Collection (EBSCOhost) – printed on 3/13/2020 4:15 PM via YORKVILLE UNIV
AN: 1595320 ; Project Management Institute.; A Guide to the Project Management Body of Knowledge (PMBOK® Guide)–Sixth Edition
Account: s7439054

What Will You Get?

We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.

Premium Quality

Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.

Experienced Writers

Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.

On-Time Delivery

Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.

24/7 Customer Support

Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.

Complete Confidentiality

Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.

Authentic Sources

We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.

Moneyback Guarantee

Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.

Order Tracking

You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.

image

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

Areas of Expertise

Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.

image

Trusted Partner of 9650+ Students for Writing

From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.

Preferred Writer

Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.

Grammar Check Report

Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.

One Page Summary

You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.

Plagiarism Report

You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.

Free Features $66FREE

  • Most Qualified Writer $10FREE
  • Plagiarism Scan Report $10FREE
  • Unlimited Revisions $08FREE
  • Paper Formatting $05FREE
  • Cover Page $05FREE
  • Referencing & Bibliography $10FREE
  • Dedicated User Area $08FREE
  • 24/7 Order Tracking $05FREE
  • Periodic Email Alerts $05FREE
image

Our Services

Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.

  • On-time Delivery
  • 24/7 Order Tracking
  • Access to Authentic Sources
Academic Writing

We create perfect papers according to the guidelines.

Professional Editing

We seamlessly edit out errors from your papers.

Thorough Proofreading

We thoroughly read your final draft to identify errors.

image

Delegate Your Challenging Writing Tasks to Experienced Professionals

Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!

Check Out Our Sample Work

Dedication. Quality. Commitment. Punctuality

Categories
All samples
Essay (any type)
Essay (any type)
The Value of a Nursing Degree
Undergrad. (yrs 3-4)
Nursing
2
View this sample

It May Not Be Much, but It’s Honest Work!

Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.

0+

Happy Clients

0+

Words Written This Week

0+

Ongoing Orders

0%

Customer Satisfaction Rate
image

Process as Fine as Brewed Coffee

We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.

See How We Helped 9000+ Students Achieve Success

image

We Analyze Your Problem and Offer Customized Writing

We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.

  • Clear elicitation of your requirements.
  • Customized writing as per your needs.

We Mirror Your Guidelines to Deliver Quality Services

We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.

  • Proactive analysis of your writing.
  • Active communication to understand requirements.
image
image

We Handle Your Writing Tasks to Ensure Excellent Grades

We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.

  • Thorough research and analysis for every order.
  • Deliverance of reliable writing service to improve your grades.
Place an Order Start Chat Now
image

Order your essay today and save 30% with the discount code Happy