[Subject]
Revision
:
1.0
Project Charter
Date
:
March 22nd, 2020
[Company] |
Project Charter –
Date – March 22nd, 2020
Approved – Kevin Shah, CEO, Commscope
[Subject]Project Charter
PMGT 699 Project Charter v.1 April 2018 (Adapted from Document Code: PMBOK4.1.3.1)
Date | Revision |
Description |
Author |
March 22nd, 2020 | 1.0 |
Publication for use |
Raj Chelikani |
Table of Contents
1.
General Provisions
4
2.
Terms, Notations, Abbreviations
4
3.
Project Purpose
4
4. Measurable Project Goals and Objectives 5
5. High-level Project Description and Boundaries 6
6.
High-Level Requirements
6
7.
Overall Project Risk
7
8. High Level Constraints and Assumptions 7
9.
Summary Milestone Schedule
7
10.
Key Project Deliverables
7
11.
Preapproved Financial Resources
8
12.
Key Stakeholder List
8
13.
Project Approval Requirements
9
Project Exit Criteria
9
Project Manager
9
Appendixes
10
1.
General Provisions
This document refers to the project “[Subject]”, which is implemented by the organization “[Company]”.
The Project Charter formulates the practical requirements and documents the high-level description of the product, service or other deliverable that should meet these requirements and will be result of the project.
The Project Charter is issued and signed by the Initiator or Sponsor of the project and formally legitimized the existence of the project. It provides the Project Manager with the authority to use the organizational assets in the project operations.
The approved Project Charter formally initiates the project.
If the project consists of several phases, the Charter can be updated to verify or improve the decisions taken during the previous iteration of the Project Charter development. In such a case the Charter is re-issued and signed as amended.
Terms, Notations, Abbreviations
Term/Abbreviation
Definition
DAS
Distributed Antenna System
RF
Radio Frequency
VoIP
Voice over internet protocol
IDF
intermediate distribution frame
MDF
main distribution frame
CDF
combined distribution frame
Project Purpose
The Dallas Cowboys’ new stadium in Arlington, Texas, the nation’s largest and most spectacular domed venue. Befitting a site of this stature, it will operate the most sophisticated, high-performance and world-class communications infrastructure of any sporting facility in the world. On the wireless side, more led to more—more subscribers consuming more data meant that AT&T needed more antennas and sectors to provide more capacity within the stadium. Five major upgrades were implemented to the state-of-the-art distributed antenna system (DAS).
The original goal was to build a flexible neutral host infrastructure that enabled every fan to quickly and easily tweet, text, share photos and stream videos from a wide variety of smart devices—with the stadium at maximum capacity. The current challenges that needs to be fulfilled to meet the capacity.
The Cowboys DAS is AT&T’s largest DAS stadium project and has been a model for others across the country. Below are the detailed project proposal and purpose.
· Hundreds of antennas will be added to provide coverage throughout the venue.
· Dozens of cell sites located in the stadium will be doubled the number of last season
· Expanded AT&T’s network capacity and coverage on the DAS system by more than 150%.
We’ve taken steps to better manage the large amount of wireless traffic we expect to see during this week across Dallas-Fort Worth.
· Install Distributed Antenna Systems (DAS) throughout major hotels and venues hosting football teams and fans throughout the Dallas-Fort Worth metroplex.
To better serve the areas in and around Cowboys Stadium, we should also add:
· Equipment installation to a temporary Outdoor DAS that consists of five additional network zones that will provide added coverage in the stadium parking lot .
· Enhanced coverage at teams practice fields and Cowboys HQ
This will provide additional capacity to cell sites in the vicinity of the stadium and serving the facilities where the teams will be practicing.
Federal Communication Commission approvals and before and after installation and during launch is required. Must follow all local radio emission precautions and display signs where needed.
Organizational need
· Customer request (e.g., an electric utility authorizing a project to build a new substation to serve a new industrial park)
· Technological advance (e.g., an electronics firm authorizing a new project to develop a faster, cheaper and smaller laptop after advances in computer memory and electronics technology)
· Legal requirement (e.g., a paint manufacturer authorizing a project to establish guidelines for handling toxic materials)
· Ecological impacts (e.g., a company authorizing a project to lessen its environmental impact)
· Social need (e.g., a nongovernmental organization in a developing country authorizing a project to provide potable water systems, latrines and sanitation education to communities suffering from high rates of cholera).
These factors may also be called incentives, opportunities or business requirements. The basic point of all these factors is that management should decide what the response should be to them, and what projects should be authorized and fixed in the Charter.>
Measurable Project Goals and Objectives
The Major goals of the project is to achieve the below business goals
Business Goal 1:
· Project Objective 1.1: The Company had decided to add additional network infrastructure and Cellular sectors to the stadium to meet the capacity increase the user experience.
· Project Objective 1.2: A dedicated antenna within every stadium suite
· Project Objective 1.3: Expanding ION-E distribution system throughout the parking lot area to give tailgaters swift, 24/7 wireless access along with MIMO coverage inside via dedicated secondary antennas in support of for future Super Bowl events.
Business Goal 2:
· Project Objective 2.1: Adding 150 intelligent point-of-interface modules to the ION-E platform to support 15 zones of parking lot coverage for AT&T
· Project Objective 2.2: Expanding the core DAS headend area from two to six rooms.
Business Goal 3:
· Project Objective 3.1: Adding 500 ION-E remotes and 400 antennas to the lower concourse via a lockable façade that optimizes capacity closer to the fans without compromising any aesthetics.
· Project Objective 3.2: Adding 100 ION-E remotes to the upper concourse.
· Project Objective 3.3: The state-of-the-art DAS manages more than 20 stadium functions, including ticketing, halftime staging, maintenance and team communications. Between 2016 and the beginning of 2020, the total antenna count rose nearly 60 percent, from 1021 to 1687. Guided by the principle that signal strength should be “used, not seen”, every single antenna in the building is hidden from the naked eye.
High-level Project Description and Boundaries
With today’s advanced networks and the proliferation of smartphones, it’s easy to understand how traffic has increased at major venues just as it has everywhere else, and why AT&T has seen a 2,300% increase in mobile data on its network over just the past three years (3Q07 to 3Q10). Through venue enhancements, such as Cowboys Stadium, AT&T continues to provide a great customer experience whether you’re making calls, checking e-mail, downloading the latest scores, or surfing the Internet on your AT&T device.
· Host internationally televised events on a massive scale
· Integrate all systems via a converged infrastructure
· Support wireless capacity equal to an entire stadium
· Build scalability and redundancy into all systems
High-Level Requirements
All the High-level Requirements from all parties have to listed and documented.
A. General:
1. The DAS shall be installed with Management, а Monitoring System.
2. The DAS shall be remotely monitored by Contractor.
3. The Management and Monitoring System shall provide for interactive interfaces to all major DAS electronic components including base head-end, remote units, antenna points, and power supplies. The DAS components shall be interfaced to the facility’s converged data network.
4. The Management and Monitoring System shall allow for real-time remote management and monitoring of the DAS.
5. The Management and Monitoring System shall have a customizable graphical user interface (GUI) for visual display and indication of system status. The GUI shall include the following minimum criteria:
a. Facility maps with interactive equipment icons of major system components and antenna locations.
b. Interactive equipment icons, color coded to indicate current status and clickable by mouse to show device information, status, log, configuration, etc. B. System Features:
C. The Management and Monitoring System software shall incorporate the following features:
1. Remote Equipment Configuration and Troubleshooting
2. Graphical User Interface (GUI)
a. Facility Maps with Interactive Icons (equipment and antennas)
b. Color coded icons for quick visual reference.
c. Equipment Status (threshold, status, alarm, etc.)
3. Alarm Notification
a. Equipment and Antenna Status
4. Web Based Access
a. VPN credentials and User Login
b. Remote Diagnostics
5. Logs
a. Status
b. Alarm and Events
c. History
d. Performance
e. Maintenance
f. Users
g. System Inventory
h. Configurations
6. Maintenance Schedule, Alerts, Reminders, Notification, and Logs
7. System Administration
a. Administrator Login, Passwords, and Security Access Level
b. Users Login, Passwords, and Security Access Level
D. System Requirements
1. Operating System: Windows 7 or Windows 8.
2. Equipment Networking: Ethernet 10/100/1000 Mbps (RJ45 Jack).
Requirements include the quantified and documented needs, wants and expectations of the Sponsor, Customer and other stakeholders of the project. The Project Charter contains high-level requirements only. A complete list requirements should be developed later in the Project Management plan as they become more concrete during the gradual elaboration of the project.
Overall Project Risk
Overall High level project risks.
Construction Risk – There could be several construction risk could come up if the site is not properly surveyed. And the mitigated risk should be updated in the new versions of the plumbing diagram.
Engineering risks – These risk come with handling the testing procedures. Identifying a faulty or damaged equipment during the testing needs to be notified to the project manager and RMA the part at the earliest.
Integration Risks – The planning integration with the AT&T live signal of commercial purpose the mandatory E911 test needs to pass. If the test failed the network cannot be deployed in to commercial status.
Perform risk analysis and maintain a risk register and a risk management plan to mitigate any risks that are caused in the project. Categorize them to risk category and a brief description and a cause for the risk.
Please note that the Project Charter contains high-level risks only. The complete list of risks should be presented in the Risk Register.>
High Level Constraints and Assumptions
Challenges are expected in such large scale project
Constraints:
· Constraint 1
· Constraint 2
· Constraint 3
Assumptions
· Assumption 1
· Assumption 2
· Assumption 3
Summary Milestone Schedule
No.
Milestone
Responsible Party
Date
1
Evaluate and Survey
Government relations and Implementation Team
04/03/2020
2
RF design and Plumbing
Engineering
04/17/2020
3
Construction
Construction
05/20/2020
4
Testing
Engineering
05/29/2020
5
Pre-Launch
Tech Support
06/12/2020
6
Launch
Network Operations
06/19/2020
Key Project Deliverables
Deliverables
Date Available
Acceptance Criteria
Survey Document/Report
04/01/2020
Reports must be documented with all the approvals and must be signed off from a Licensed Professional Engineer
Final RF Design Document
04/15/2020
Final RF design must be approved from carrier AT&T engineering
Government (FCC) Approvals
04/24/2020
FCC approvals needed for the RF Emissions
Fire Dept Notice Documents
05/08/2020
All Fire codes and procedures and inspections need to be approved.
System Testing and Walk reports
05/28/2020
Continuous wave testing from system and continuous wave walk reports needs pass
Post Integration Workbook
06/17/2020
Record all Emissions, Downlink, Uplink and Signal Strength are required and documented.
Post Integration Walk Reports
06/18/2020
Live Signal Walk test reports need to be submitted.
RF Post Integration Optimization Summary
06/19/2020
Post integration optimization reading needed to be documented.
Preapproved Financial Resources
Аs a total cost of $38.725 million, the gigantic 100,000-seat Stadium houses the world’s largest IPTV—a four-sided, 600-ton suspended LED scoreboard—and nearly 950 miles of Commsope cabling, roughly the equivalent of a one-way road trip from Arlington to Chicago.
Project Costs
USD
Human resources
$4,500,000
Evaluation
$75,000
Design
$150,000
Construction
$5,000,000
Testing
$400,000
Pre Integration Testing
$400,000
Pre-Launch
$400,000
Launch
$200,000
Optimization
$500,000
KPI Monitoring
$100,000
Total
$11,725,000
Equipment Costs
USD
Software Upgrades
$1,000,000
Hardware Upgrades
$15,000,000
New Hardware
$4,000,000
Fiber
$1,500,000
New Cable
$500,000
Total
$22,000,000
Reserve Cash
$5,000,000
Key Stakeholder List
Full Name
Position/Organization
Role in the Project
Telephone/E-mail
Kevin Shah
CEO, Commscope
Sponsor, Managing funds
Kevin.Shah@commscope.com
Amith Patel
CIO, AT&T Mobility
Sponsor, Project oversight
amith.patel@attmobility.com
Raj Chelikani
Project Manager
Client Communication, Scheduling and Co-ordination
Raj.chelikani@commscope.com
Mike Simpson
Design Engineer
Design Schematics and simulation plots
Mike.simpson@commscope.com
Naveen
RF Engineer
Testing, troubleshooting and managing site activities
Naveen.katakam@commscope.com
Daniel Rauf
Construction Manager
Overseeing the construction activities
Daniel.rauf@commscope.com
Shawn Addison
Network Operations
Managing network operations and maintenance
Shawn.addison@commscope.com
Project Approval Requirements
The main approvals the are required for the project are
· Site Audits and Inspections.
· Project Area audits.
· Local and municipal Permits.
· FCC regulatory Filings and approvals.
· RFDS (Radio Frequency Data Sheets) for final online integration.
· Signal strength covering more than 95% of the venue.
· Able to achieve high speed data rates.
· Reduce the instance of drop calls.
· Improve the KPI performance.
· Increasing the call capacity and Bandwidth per sector.
This specification is intended to establish the minimum performance criteria requirements for providing a neutral host distributed antenna system (DAS). The contractor shall coordinate all system and performance requirements and criteria with all DAS users to ensure signal strength, coverage, capacity, and other requirements are all maintained. This includes coordination with Cellular Carriers.
All the approvals need to obtain before the initiation and the success criteria depends on the our ability
To provide the customers a seamless and Uninterrupted services to the customers. These upgrades
Will provide the audience with handling more than twelve terabytes of data for each game.
Project Exit Criteria
Project exit criteria depends on the overall performance of the project from the initiation to the end deliverables.
The entry and exit criteria of the project certainly depends upon the requirements and the final deliverables that are delivered. The project is chosen depending upon the requirements and a realistic valuation of the project and the ability to complete on time. All certain things have to be properly documented, understand, utilize resources and then bid for the project. The exit criteria depends on the final deliverables and the closeout package to the customer and making sure that the everything is delivered to the customer in as promised in the charter. Evaluating the documentation and archive them for future use such as any additions or changes that are necessary to the existing system.
Engineering Closeout – The engineering team is responsible for preparing the closeout package which includes the walk reports for the venue the readings that are measured at the system under the installed equipment locations detailed photographic pictures of all installed equipment and antennas that are located in the venue all exports from the walk data.
Construction Closeout – The construction team is responsible for the all the plumbing documentation closeout. And also report the constrains and challenges that are faced.
Implementation Closeout – Final project signoff and the handing over the network control to AT&T.
Project Manager
Project manager is responsible for the passing the client requirements to the constriction and engineering teams, maintain communication and co-ordination between teams. Tracking the project process and reporting it to the management, performing risk analysis and plan risk mitigation accordingly. Planning and scheduling with other portfolios and passing the communication accordingly for the activities that needs to be performed each week and monitoring the process. Maintain, prepare documentation that is required for the teams.
Signed/Project sponsor(s) or charter approving authority
Approval and Authority to Proceed
We approve the project component as described above, and authorize the team to proceed.
Name
Title
Role
Date
[type or sign name]
Appendixes
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.