Introduction
CE 2.1
I did this project as a graduate Electrical Engineering while pursuing my Bachelor of Engineering in the field of Electrical Engineering from Balochistan University of Engineering and Technology, Balochistan. I wanted to conduct a project that would be challenging and would involve how to improve the existing power grid by helping the current or load at a given time. I wanted to create a system by improving the power factor or changing the conductor size or substituting the cables with conductors. I was able to improve my written and oral presentation skills as well as my interpersonal skills by the successful completion of this project.
Background
CE 2.2
For this project as an undergraduate student in electrical engineering, I wanted to start working on a project that would be challenging. I wanted to learn about the different and commonly used electrical/electronic components, the working mechanism and the implementation in a common every-day system. Feeder configuration is a very important step to enhance the quality and reliability of a distribution system. During my studies, I had learned that traditionally, in Pakistan, the feeder configuration is done by opening/closing or tie & sectionalizing the switches in order to alter network map and thus the flow of power from substation to customers.
Get Help With Your Essay
If you need assistance with writing your essay, our professional essay writing service is here to help!
Essay Writing Service
I had studied during my bachelors that the reason Feeder configuration is done is to reduce system power loss and also for load balancing. As the loading conditions change, it is important to reconfigure it to reduce power losses in the network. And it is due to this reason that I selected the “Reconfiguration of 11KV Feeder” for my project.
CE 2.3
The objective of my project is to design a system to reconfigure the network for loss reduction for 11KV feeder. Or the reconfiguration of the distribution network under normal operation to reduce active losses and to balance loads in the system.
CE 2.4
CE 2.5
I first had to conduct a detailed literature review to find the best applicable approach to this system for reconfiguration.
I decided to use Branch exchange and Loop cutting methods along with a theoretical Heurestic approach to achieve my objectives.
I used the computer software for “ELR” to analyse the feeder and to calculate the results.
I initially, used an existing configuration based on actual data to calculate the current Energy Loss Reduction (ELR)
I then tabulated all the results and obtained a schematic diagram to show my results.
I completed the project within the time frame specified by the university.
I presented my findings to my supervisor.
Personal Engineering Activity
CE 2.6
I approached a senior professor with an idea of conducting a project about the power grid. Along with my group members, I had a lot of brainstorming sessions and review meetings with my project supervisor to select a suitable topic. I suggested that I work on a project that was concerned with restructuring the power grid to minimize distribution losses and we suggested that we select a suitable location for this project to be carried out and thus the topic “Reconfiguration of 11KV feeder” came in to being and the supervisor agreed to this and asked us to begin working on this by first conducting a literature review on all the components we would require and the working of this project and to start working on this project.
CE 2.7
I decided to select a Surab Town feeder of 11KV which starts from the 132KV Pakistan Railway Grid Station. I found that this grid has two transformers connected in parallel having a capacity of 10/13MVA each and 132/11KV. This particular feeder provided power of mixed loads to residential, commercial, agricultural and gas power plants. I carried out the Physical Survey of the existing 11KV Surab Town Feeder and plotted a Single line diagram of existing Surab town feeder.
I calculated the energy losses and voltage drop of existing distribution system keeping in view the QESCO requirements. The length of feeder is 42.62km with annual energy loss 457898.1kWH and maximum percentage voltage drop is 6.5%, which is beyond the specified limit of QESCO i.e. 5.0% and is not acceptable as shown in the table below.
Month
Max Hour KWH Reading in Year-3
(KWH)
Units Sent in Year-3
(KWH)
Units Sold in Year-3
(KWH)
Losses
KWH
%
January
0920108
0922574
1954326
1020746
933580
47.8
February
1809123
1811499
1504110
785804
719490
47.8
March
2577218
2580502
1233398
1324005
-90607
-7.3
April
2944920
2946703
1695002
1472175
223911
13.2
May
4197868
4199507
1758256
1693000
65256
3.7
June
4483081
4485732
1472868
1392621
84892
5.8
July
5663010
5665217
1452128
1146852
303276
21.0
August
6179532
6174379
1272432
1263513
8919
0.7
September
72162
76150
1636414
5107276
129138
7.9
October
1747258
172496
2070467
1654039
418057
20.2
November
4868322
4873227
2704009
1584898
1119111
41.4
December
6046270
602780
3086286
1626763
1459523
47.3
I used the following simple algorithm for the algorithm:
Start with an existing configuration.
Read Input data..Run ELR program..Display results..Compare KWH losses,
If KWH loss CE 2.8
My test system is a high loss, problematic distribution feeder of QESCO. In first, the existing Grid and feeder data are collected from Surab grid station. The data made run in ELR Software, which results high losses due to overloads. As the ampere load accedes then 300 amp on main Dog conductor , To overcome these overloads we recon figurate the feeder by using three different methods i.e. Branch Exchange Method, Loop Cutting Method and then we applied bifurcation method to isolate the existing feeder into two parts.
I collected data from the Head office QESCO in Quetta, Pakistan and found that the monthly Peak Load is between 600-700 Amps and the off peak load between 5-90 Amps with the lowest being in November.
I conducted a Load flow analysis was done using ELR Program with the following input Parameters at 5% annual Load growth rate
Load in Amp.=395 Amp @ 5% for 5 years
Bus Voltage=11KV
Feeder load factor=6.29%
Existing power factor=0.78%
Proposed power factor=0.79%
Capacitor installed=2Nos.
I proposed the following one line diagram of QESCO feeder as prepared on the basis of field visits is shown below in figure. This figure clearly shows the difference between actual and proposed configuration of the feeder. In this figure 154 node are shifted. Also the route of power flow has been changed there by feeding all the consumers.
This configuration has reduced the line losses too as evident from the load flow analysis. The details are feeder given below.
Power T/F # ΙΙ
Feeder code 020201
Power T/F capacity 10/13 MVA
Number of node 92
Number of transformers 66
Number dog conductor 18
Number rabbit conductor 73
Total length of line 18.42 KM
Total KVAS 5350 KVA
I also proposed and conducted a Load flow analysis using ELR Program with the following input Parameters at 5% annual Load growth rate.
Load in Amp= 395A@5%for 5 years
Bus Voltage = 11KV
Feeder load factor= 6.29%
Existing power factor = 0.78%
Proposed power factor = 0.95% (Improved Due to capacitor Placement)
CE 2.9
I conducted this project successfully and found that the ELR program could be used sappropriately and properly to find the optimal configuration of 11KV feeder, demonstrating the feasibility of such an approach for the solution of this problem.
However, refinements to the algorithm may be necessary in order to achieve satisfactory performance on large, real-world systems consisting of thousands of buses.
The following were my results:
Losses (KWH) minimized from 457898 to 332944
Voltage drop improved from 6.5% to 4.4%
Power Factor improvement from 0.78% to 0.95% (Result of proposed configuration)
B/C Ratio is 24.25
CE 2.10
My contribution during this project was:
Gathering Exact Grid data on realistic approaches.
Gathering feeder data, one line diagram preparation physically through field visits.
Exact measures and distances of node-to-node and exact electrical parameters information’s. Keeping in view different constraints, like Cost, Obstacles, Load. Losses, Environmental / social constraints, Betterment of WAPDA as well as general public.
Re-notification of existing configuration and finding the optimal configuration by repetition the results obtained after execution of ELR Program.
Removing haphazard road crossings and reducing the length of feeder.
Load Balancing.
Placement of Capacitor at best locations for obtaining best results.
Summary
CE 2.9
I successfully completed the project titled “Reconfiguration of a 11KV Feeder” along with my team members. I learned how to reconfigure a 11KV feeder and about the different approaches by execution of the ELR program I learned how to gather Grid data for realistic approaches to improve loading.
By the successful completion of this project, I was able to improve my written, oral and interpersonal skills. I was also able to improve my team work.
The main objective of this research is to develop methodology and guide lines for distribution engineers to show that by reducing the energy losses of distribution system, available capacity of the system may be conserved without putting up additional capacity. A generalized computer program is used to evaluate any given HT/LT system and propose capacitor banks at different points, different conductor sizes in different portions of system. This results in improving the stability as well as energy handling capacity of the system at minimum cost.
We provide professional writing services to help you score straight A’s by submitting custom written assignments that mirror your guidelines.
Get result-oriented writing and never worry about grades anymore. We follow the highest quality standards to make sure that you get perfect assignments.
Our writers have experience in dealing with papers of every educational level. You can surely rely on the expertise of our qualified professionals.
Your deadline is our threshold for success and we take it very seriously. We make sure you receive your papers before your predefined time.
Someone from our customer support team is always here to respond to your questions. So, hit us up if you have got any ambiguity or concern.
Sit back and relax while we help you out with writing your papers. We have an ultimate policy for keeping your personal and order-related details a secret.
We assure you that your document will be thoroughly checked for plagiarism and grammatical errors as we use highly authentic and licit sources.
Still reluctant about placing an order? Our 100% Moneyback Guarantee backs you up on rare occasions where you aren’t satisfied with the writing.
You don’t have to wait for an update for hours; you can track the progress of your order any time you want. We share the status after each step.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
Although you can leverage our expertise for any writing task, we have a knack for creating flawless papers for the following document types.
From brainstorming your paper's outline to perfecting its grammar, we perform every step carefully to make your paper worthy of A grade.
Hire your preferred writer anytime. Simply specify if you want your preferred expert to write your paper and we’ll make that happen.
Get an elaborate and authentic grammar check report with your work to have the grammar goodness sealed in your document.
You can purchase this feature if you want our writers to sum up your paper in the form of a concise and well-articulated summary.
You don’t have to worry about plagiarism anymore. Get a plagiarism report to certify the uniqueness of your work.
Join us for the best experience while seeking writing assistance in your college life. A good grade is all you need to boost up your academic excellence and we are all about it.
We create perfect papers according to the guidelines.
We seamlessly edit out errors from your papers.
We thoroughly read your final draft to identify errors.
Work with ultimate peace of mind because we ensure that your academic work is our responsibility and your grades are a top concern for us!
Dedication. Quality. Commitment. Punctuality
Here is what we have achieved so far. These numbers are evidence that we go the extra mile to make your college journey successful.
We have the most intuitive and minimalistic process so that you can easily place an order. Just follow a few steps to unlock success.
We understand your guidelines first before delivering any writing service. You can discuss your writing needs and we will have them evaluated by our dedicated team.
We write your papers in a standardized way. We complete your work in such a way that it turns out to be a perfect description of your guidelines.
We promise you excellent grades and academic excellence that you always longed for. Our writers stay in touch with you via email.